Supply of all fabricated items for the complete tank farm.
Normand and Thomson have supplied many tank farm projects throughout the UK and Europe. For this UK project Normand and Thomson were selected as the main contractor for the design and supply of 12 tanks and pipe work ranging from 1/2" to 12", as well as structural steel. Working in close collaboration with process, structural, civil and E&I engineers as well as the end user,  Normand and Thomson carried out design of steelwork and piping routings. All materials were procured by N&T. Manufacturing of tanks, pipe work and steelwork was carried out in our facility in Dalgety Bay, and shipped to site for assembly by our staff using our own lifting equipment. Additionally Normand and Thomson installed all other mechanical plant including heat exchangers, grinders, pumps, valves and instrumentation. The project was completed in five months to the complete satisfaction of our customer.Â